Tuesday, October 19, 2010

part 2: The new rail link

Within minutes through the Alps

The Gotthard axis consists of a new rail link from Arth Goldau to the Lugano area and includes a new Gotthard Base Tunnel. This is the heart of the flat rail link for travel through the Alps. The north portal of the Gotthard Base Tunnel is north of Erstfeld, the south portal at Bodio.


Image Source: Alp Transit Gotthard AG

The length of the Base Tunnel is approx. 57 km. Intermediate points of attacks are planned in Amsteg, Sedrun and Faido. The tunnel is scheduled to be completed in 2015. For a total length of 57 km and a planned train speed of 200 km/h the advance rate per day is 20 to 40 metres in shift operation. 2000 miners and engineers are working here. This is a major logistical challenge for the material transport.


Image Source: Alp Transit Gotthard AG

The equipment
At the construction site a diesel-hydraulic monorail transports concrete skips, all materials for rock protection and the tunnel boring machine (TBM), girders, big bags, machine parts, rails and sand containers.

The hydraulic monorail is a universal means of transport. It enables transport without handling and a mains independent transport system thanks to the diesel engine.

Because of the high demands a PLC, a CAN communication bus as well as the CANopen protocol are used.

Requirement:
  • Mechanical stability in case of extreme shocks
  • Use over low and high temperature ranges
  • Direct influence of dirt and water
  • High fluctuations of the supply voltage
  • High electromagnetic compatibility
  • E1 approval from the German Federal Office for Motor Traffic


Image Source: Alp Transit Gotthard AG

Here the technical data:
  • Application: ARGE Amsteg (CH)
  • Machine type: diesel-powered monorail locomotive
  • Transport task: concrete skips and goods
  • Drive: diesel-hydraulic
  • Power: 110 KW
  • Tractive force: 40 kN
  • Speed: 2 m/s
  • Inclination: 1%
  • Max. load: 19 t
  • Total weight: 32 t
  • Control: radio remote control
  • Particularities: transponder system, remote diagnosis



Gotthard tunnel breakthrough!

Monday, October 18, 2010

Within minutes through the Alps

Part 1: The project

As of 2015 high-speed trains will race through the Alps. Milelong jams in incredibly long tunnels will belong to the past once the Gotthard Base Tunnel project has been completed.


Image source: Alp Transit Gotthard AG

Preliminary work on the project started in Sedrun in 1996. Since then colossal boring machines have been making their way through the age-old rocks of the Alps.


Image source: Alp Transit Gotthard AG

In the main mountain range of the Alps drilling is done at five locations in three different cantons (Uri, Ticino, Graubünden). The 153 km long tunnel and shaft system will cost approx. 10 billion Swiss francs. The huge project is a challenge for engineers: sliding soft rocks, tunnel boring machine standing in water or enormous pressure forcing down steel girders. A great deal is, of course, required of technology. Actually, conditions can hardly be any harsher: extremely rough environment, much dust caused by blasting, moisture because of mountain water, high vibrations and temperature fluctuations. Sensors and controllers must be able to take a lot.


Image source: Alp Transit Gotthard AG

More information about the project:

»»» http://www.alptransit.ch/en/

Part 2 provides information about the construction of the new rail link from Arth Goldau to the Lugano area and the technology used.